A milestone's issue counts (#15839)
A milestone's page says, in the muted line beside its progress bar, how many of its issues are
open and the day the last done one landed: 1 open · landed 2026-10-22. The done count is
the bar's own (2 of 3 done), so it is not said twice. Until something has landed the line names
no date. An issue closed as not doing is neither done nor open.
- Page:
/<owner>/<name>/milestones/<number>, the line under the title (#ms-counts). - API:
GET /api/v1/repos/:owner/:name/milestones/:numbercarriesissues: {done, open, lastLanded, words};lastLandedisYYYY-MM-DDor null,wordsreads2 done, 1 open, last landed 2026-10-22,0 done, 2 open, none landed yet, orNo issues yet.. - MCP: the
milestonestool withissueanswers the sameissuesobject (there is no separatechangelogorstorytool for a milestone;releasesis the changelog and does not read it).
Try it: close one issue under a milestone and open its page.